Jordskred ved Nordic Waste – ref NRK nyhetsoppslag. Les mer.
Contaminated soil

Eramet Kvinesdal

WMR engaged by Kvina Maskin to handle contaminated hazardous soil from groundworks at ErametKvinesdal.

The soil was loaded in vessel designed to carry non stable hazardous soils and transported to Miljøteknikk in Rana. Stable and non reactive hazardous soil was transported by WMR to nearby Svåheia Landfill who has a dedicated cell in the landfill for such waste.

A total of approx 8.000MT was handled in this project.